top of page
road 2.jpg

PROPOSED EVERGREEN TOWNSHIP 2022 ROAD PROJECTS

The following roads contracts were signed for 2022:

  1. Chloride gravel roads three (3) applications 39.95 Miles @ 1,650 GPM X 3 applications X $0.175/gallon = $34,606.69. Applied around Memorial Day, 4th of July and Labor Day

  2. Asphalt overlay on Colby Road from Staines Road to Stevenson Road (1.0 Mile) = $83,334 (minus 20% discount from MCRC)

  3. Asphalt overlay on Colby Road from Stevenson Road to Town hall Road (1.0 Mile) = $87,583 (minus 20% discount from MCRC)

  4. Spray brush along local roadsides to be determined by township and road commission = $2,000

  5. Provide eighty (80) hours of ditching along local roads. Locations to be determined by the township and road commission 80 hours @ $125 per hour = $10,000

  6. Machine wedge and seal on Holland Lake Road from Staines Road to Stevenson Road with remove/replace asphalt at the Evergreen Extension Drain = $33,488 (Minus 15% discount from MCRC)

  7. Limestone Townhall Road from Muskrat Rd to Holland Lake Rd. (1.0 Mile) = $41,691.65. (Minus 15% discount from MCRC)

  8. Rotomill and pave Staines Road from Beardsley Road to Muskrat Road (0.5 Mile) = $78,269. (Minus 20% discount from MCRC)

EVERGREEN TOWNSHIP 2021 ROAD PROJECTS

The following roads contracts were signed for 2020:

  1. Spray brush along local roadsides to be determined by township and road commission = $2,000

  2. Gravel resurface Stevenson Road from Sidney Road to Colby Road (1.0 Mile) = $17,360

  3. Gravel Resurface with limestone Townhall Road from Condensery Road to Muskrat Road (1.0 Mile) = $46,142

  4. Machine wedge and sealcoat on Holland Lake Road from Stevenson Road to Townhall Road (1.0 Mile) = $27,957

  5. Sealcoat with fog seal Dorothy Bowen Drive from Holland Lake Road to the end (0.50 Miles) = $6,331

  6. Sealcoat with fog seal Holland Lake Road from Townhall Road North to Wicker Road (1.0 Mile) = $18,089

  7. Sealcoat with fog seal Staines Road from Sidney Road North to end of pavement (0.25 Miles) = $4,404

  8. Three applications of chloride on local roads at the rate of 1,650 gallons per mile (39.95 Miles) = $34,606.69

  9. Provide forty (40) hours of ditching along local roads. Locations determined by the Township and MCRC = $5,000

EVERGREEN TOWNSHIP 2023 ROAD PROJECTS

  • Road contracts signed for 2023 contract year.

  1. Three applications of chloride on local roads 40.24 miles @1.650 GPM x 3 applications x $0.180/gallon = $35,853.84

  2. Asphalt overlay Staines Road to Stevenson Road (1.0 mile) = $120,317.00 (road commission to deduct $50,000.00 from this total) = $70,317.00

  3. Brush spray along roadsides to be determined.  Cost to be shared, the road commission to contribute $2,000 to match township contribution. = $,2000.00

  4. Provide eighty (80) hours of ditching along local roads.  Locations to be determined by the township and road commission = $10,000.00

  5. Gravel re-surface Senator Road from Pakes Road to CR522 (0.95 Miles) to be shared with Crystal Township.  Evergreen Township share = $7,234.00

  6. Limestone resurface Beardsley Road from Stevenson Road to Townhall Road (0.75 Mi) = $41,395.00

  7. Limestone resurface Beardsley Road from Staines Road to Stevenson Road (1.25 Mi) = $68,992.00 (Road Commission to deduct $13,000 price for gravel resurface mile) = $55,992.00

  8. Overband crack seal locations to be determined by township and road commission. 7,500 lbs crack seal emulsion = $8,775.00

Total to be spent on road projects $231,567.34 for 2023-2024