EVERGREEN TOWNSHIP 2024 ROAD PROJECTS

ROAD CONTRACTS BETWEEN MONTCALM COUNTY ROAD COMMISSION AND EVERGREEN TOWNSHIP FOR 2024-2025 SEASON

1.  THREE applications of chloride on local roads at a rate of 1,650 gallons per mile 39.67 MI @1,650 GPM x 3 appllications = $35,345.97
2. Limestone resurface Pakes Rd from M-66 (Sheridan Road) East 1.0 Mile $60,509
3.  Sealcoat with fog seal on Colby Road from Staines Road to Stevenson Road 1.0 Mile $18,629
4. Asphalt overlay on Beardsley Road from Sheridan City Limit east to end of pavement .25 Mile $31,462
5. Provide Forty (40) hours of ditching along local roads, locations to be determined by the township and MCRC $5,000

6. Asphalt overlay on Holland Lake Road from Vickeryville Road to Senator Road 0.5 Mile $90,938

Total to be spent on road projects $207,373.97 for 2024-2025

EVERGREEN TOWNSHIP 2023 ROAD PROJECTS

​ROAD CONTRACTS BETWEEN MONTCALM COUNTY ROAD COMMISSION AND EVERGREEN TOWNSHIP FOR 2023 SEASON

  1. Three applications of chloride on local roads 40.24 miles @1.650 GPM x 3 applications x $0.180/gallon = $35,853.84

  2. Asphalt overlay Staines Road to Stevenson Road (1.0 mile) = $120,317.00 (road commission to deduct $50,000.00 from this total) = $70,317.00

  3. Brush spray along roadsides to be determined.  Cost to be shared, the road commission to contribute $2,000 to match township contribution. = $,2000.00

  4. Provide eighty (80) hours of ditching along local roads.  Locations to be determined by the township and road commission = $10,000.00

  5. Gravel re-surface Senator Road from Pakes Road to CR522 (0.95 Miles) to be shared with Crystal Township.  Evergreen Township share = $7,234.00

  6. Limestone resurface Beardsley Road from Stevenson Road to Townhall Road (0.75 Mi) = $41,395.00

  7. Limestone resurface Beardsley Road from Staines Road to Stevenson Road (1.25 Mi) = $68,992.00 (Road Commission to deduct $13,000 price for gravel resurface mile) = $55,992.00

  8. Overband crack seal locations to be determined by township and road commission. 7,500 lbs crack seal emulsion = $8,775.00

Total to be spent on road projects $231,567.34 for 2023-2024